The excavation work will take place on Otaniementie at the Otakaari junction from Monday 25th January. Blasting will be carried out 1–3 times a day.… Lue
Early 2021 changes in traffic arrangements
About 44 per cent of the construction work of Jokeri Light Rail has already been completed, and 9,140 metres of tracks are finished.… Lue
Administrative Court rejected Patterimäki appeal
The Administrative Court of Helsinki has rejected the appeal related to Patterimäki park. On 9 July 2020, the Uusimaa Centre for Economic Development, Transport and the Environment granted the City of Helsinki Urban Environment Division a permit to deviate from the protection of the Siberian flying squirrel in the construction area of Jokeri Light Rail in Patterimäki park.… Lue
The first track section of Espoo was handed over to the City on 25 November 2020
The Jokeri Light Rail project has handed over the first fully completed track section, Leppävaarankatu, to the City of Espoo. The section handed over includes the street, tracks, traffic lights and lighting.… Lue
Why will the bus traffic on Maaherrantie be diverted in March 2021?
The old railway bridge on Maaherrantie will be dismantled in March 2021, and the bus traffic on Maaherrantie will be diverted to another route.… Lue
Tulvaniitynsilta bridge will open to pedestrians and cyclists on 8 october
Tulvaniitynsilta bridge over the Vantaa River in Pihlajisto, Helsinki is now completed, and it will be open to pedestrians and cyclists from Thursday 8 October onwards.… Lue
Leppävaarankatu to resume two-way traffic on Monday 12 October
Construction on Leppävaarankatu street in front of Sello shopping centre is at its final stages. Two-way traffic will resume on Leppävaarankatu on Monday 12 October.… Lue
The intersection of Miestentie and Otaniementie will be closed to motor vehicles in week 36.
The intersection of Miestentie and Otaniementie will be closed to motor vehicles in week 36. Pedestrian and bicycle access will remain around Miestentie throughout the construction project, but it will be rerouted according to different stages of construction.… Lue
Changes in traffic arrangements in the vicinity of Jokeri Light Rail constructions sites in autumn 2020
The construction of Jokeri Light Rail is proceeding apace. This means that the traffic arrangements in the vicinity of the construction sites are also changing.… Lue
Otaranta closed to motor vehicle traffic as of week 27
The construction of the light rail has reached the southern part of Otaniemi. In addition to building the light rail, all of the road structures are going to be renewed, including pedestrian and cycling routes.… Lue